Tušimice PV Lineage
A published Tušimice PV layout visibly names two former PHENDHEY project vehicles — FVE Tušimice alfa and FVE Triangl — inside the later project geography.

Relationship to PHENDHEY
FVE Tušimice alfa and FVE Triangl were both directly held by PHENDHEY from July to November 2022. ADI’s published layout later shows both names alongside FVE Tušimice gama.
Project context
ADI’s current reference page describes the Tušimice PV plant as 111 MWp with a valid building permit and RTB status, with output routed to the R-SAH substation. The published site layout provides a strong visual lineage link to the two former PHENDHEY SPVs.
The 111 MWp figure belongs to ADI’s later Tušimice PV project, following PHENDHEY’s earlier ownership of the named project vehicles.
Project material
A visual record of the site, system and development context behind the case.