Sahara Grid Infrastructure
Transmission-scale infrastructure linked to the later-stage PDL Transformation project context.

Relationship to PHENDHEY
PDL Transformation was directly held by PHENDHEY from January to April 2023. The project vehicle later progressed under subsequent ownership.
Project context
Earlier ADI material states that it began construction of the R-SAH 110/400 kV substation with PDL Transformation and references a 400 MVA transformer. Current May 2026 material describes the broader R-SAH site as 400/110/35 kV and the surrounding Sahara storage programme at 400 MW / 800 MWh, potentially up to 1,600 MWh.
PHENDHEY’s connection is the historical ownership of PDL Transformation; the infrastructure described here belongs to the project’s subsequent development stage.
Project material
A visual record of the site, system and development context behind the case.